Grabouw Bulk Water Upgrade

12th November 2021

Lukhozi Consulting Engineers have been appointed by the Theewaterskloof Municipality to investigate and determine the route for the dedicated rising main required to convey treated water from the Grabouw water purification plant to its Steenbras reservoir. Lukhozi are providing all engineering designs and project management services to the municipality.

Our engineers are currently working hard in phase 5.1 of the project to complete the upgrade of the pumpstation at the treatment works. This treatment works is  intended to supply both the Collinskop and Steenbras reservoirs.

Upgrade of the pumpstation supplying both the Collinskop and Steenbras reservoirs.

Our team has been hard at work, taking the design from inception to advertised tender phase in just 8 weeks!

More News

news2

THE GROWTH OF OUR CAPE TOWN OFFICE

THE GROWTH OF OUR CAPE TOWN OFFICE

news2

#LUKHOZI VALUES 7/11

#LUKHOZI VALUES 7/11

news2

NAVIGATING THE GWAING WASTEWATER TREATMENT WORKS: AN INTERVIEW WITH DANIE

NAVIGATING THE GWAING WASTEWATER TREATMENT WORKS: AN INTERVIEW WITH DANIE

news2

#LUKHOZI VALUES 6/11

#LUKHOZI VALUES 6/11