Project Complete: Willow Park 7.5 Ml Reservoir

10th Sep 2021

Lukhozi Consulting Engineers have successfully completed the design and implementation of the 7.5 mega litre Willow Park reservoir contract, with the commissioning occurring in late 2019.

This bulk reinforced concrete reservoir has an impressive diameter of 40 m and stands some 8 m tall from floor to roof. The reservoir comprises 900 m³ of strength concrete and 100 tonnes of high-tensile steel reinforcing bars.

The completion of this reservoir contributes to the bulk water services being provided by the Buffalo City Metropolitan Municipality to unlock future development for the areas south and west of the East London airport, including the much-anticipated West Bank Restitution Housing Project.

Well done to the Structural and Civil Engineering team at Lukhozi Consulting Engineers together with the Contractor, Simunye Developers cc, for delivering another quality product.

More News

news2

Lukhozi welcomes Jaundré to the team!

Lukhozi welcomes their newest team member, Jaundre’ Duvenhage, to the Cape Town office.

news2

Welcome to planet earth…Lady Alyssa

Lukhozi congratulates Jacques & Mariette Jordaan (Proud Parents) with new born baby Alyssa Jordaan.

news2

The New Guy on the Block

Lukhozi welcomes their newest team member, Renier Basson, to the Cape Town office.

news2

Fort Cox College Phase 2: Sewer Services nearing completion!

The upgrading of the Wastewater Treatment ponds at the Fort Cox Agricultural College has progressed to the point of achieving practical completion, bringing to a close this 11-month contract.