Raising the pressure
19th November 2021
Lukhozi Consulting Engineers has completed the implementation of a 400Kl elevated water tank some 30m above ground in Marselle, Boesmansriviermond in the Eastern Cape, which has been suffering low water pressure for many years.
The elevated tower forms part of the bulk services construction contract which includes water and sanitation pumpstations and bulk conveyance pipelines. The contract is on programme with commissioning planned in March 2022.
We are proud to provide engineering services that makes a direct improvement to the quality of life in the area.
Construction of the Elevated Storage Tower is still currently in progress.